| Activity ID / Unique ID | Task Name | Base Duration | Base Duration Unit | Revised Duration | Revised Duration Unit | Base Total Float | Base Total Float Unit | Revised Total Float | Revised Total Float Unit |
| A1210 | SB PREPARE SPAN 2 DECK | 160 | Hr(s) | 160 | Hr(s) | 360 | Hr(s) | 248 | Hr(s) |
| A1220 | SB PREPARE SPAN 3 T-BEAMS | 160 | Hr(s) | 160 | Hr(s) | 256 | Hr(s) | 160 | Hr(s) |
| A1700 | SB PREPARE SPAN 3 DECK | 160 | Hr(s) | 160 | Hr(s) | 360 | Hr(s) | 248 | Hr(s) |
| A1230 | SB PREPARE BENT 2 EDGE BEAM | 160 | Hr(s) | 160 | Hr(s) | 360 | Hr(s) | 208 | Hr(s) |
| A1660 | SB APPROVE SPAN 3 T-BEAMS | 120 | Hr(s) | 120 | Hr(s) | 360 | Hr(s) | 224 | Hr(s) |
| A1940 | SB APPROVE SPAN 3 DECK | 120 | Hr(s) | 120 | Hr(s) | 512 | Hr(s) | 360 | Hr(s) |
| A1670 | SB APPROVE BENT 2 EDGE BEAM | 120 | Hr(s) | 120 | Hr(s) | 504 | Hr(s) | 296 | Hr(s) |
| A1950 | SB APPROVE BENT 3 EDGE BEAM | 120 | Hr(s) | 120 | Hr(s) | 512 | Hr(s) | 304 | Hr(s) |
| A2200 | SB APPROVE BENT 4 EDGE BEAM | 120 | Hr(s) | 120 | Hr(s) | 512 | Hr(s) | 304 | Hr(s) |
| A1960 | SB APPROVE SPAN 4-6 DECK | 120 | Hr(s) | 120 | Hr(s) | 488 | Hr(s) | 352 | Hr(s) |
| A1680 | SB APPROVE SPAN 7-9 DECK | 120 | Hr(s) | 120 | Hr(s) | 288 | Hr(s) | 192 | Hr(s) |
| A2210 | SB APPROVE SPAN 1-6 BRIDGE RAIL CURB | 120 | Hr(s) | 120 | Hr(s) | 624 | Hr(s) | 416 | Hr(s) |
| A1710 | SB PREPARE BENT 3 EDGE BEAM | 160 | Hr(s) | 160 | Hr(s) | 360 | Hr(s) | 208 | Hr(s) |
| A1970 | SB PREPARE BENT 4 EDGE BEAM | 160 | Hr(s) | 160 | Hr(s) | 360 | Hr(s) | 208 | Hr(s) |
| A1720 | SB PREPARE SPAN 4-6 DECK | 160 | Hr(s) | 160 | Hr(s) | 344 | Hr(s) | 240 | Hr(s) |
| A1240 | SB PREPARE SPAN 7-9 DECK | 160 | Hr(s) | 160 | Hr(s) | 200 | Hr(s) | 136 | Hr(s) |
| A1980 | SB PREPARE SPAN 1-6 BRIDGE RAIL CURB | 160 | Hr(s) | 160 | Hr(s) | 432 | Hr(s) | 288 | Hr(s) |
| A1990 | SB PREPARE SPAN 7-9 F-RAIL | 160 | Hr(s) | 160 | Hr(s) | 592 | Hr(s) | 448 | Hr(s) |
| A1250 | SB PREPARE BENT 1 & 10 END PANELS | 160 | Hr(s) | 160 | Hr(s) | 1088 | Hr(s) | 944 | Hr(s) |
| A1650 | SB APPROVE SPAN 2 DECK | 120 | Hr(s) | 120 | Hr(s) | 504 | Hr(s) | 352 | Hr(s) |
| A2220 | SB APPROVE SPAN 7-9 F-RAIL | 120 | Hr(s) | 120 | Hr(s) | 848 | Hr(s) | 640 | Hr(s) |
| A1690 | SB APPROVE BENT 1 & 10 END PANELS | 120 | Hr(s) | 120 | Hr(s) | 1528 | Hr(s) | 1336 | Hr(s) |
| A1500 | SB FABRICATE SPAN 2 T-BEAMS | 160 | Hr(s) | 160 | Hr(s) | 264 | Hr(s) | 240 | Hr(s) |
| A1830 | SB FABRICATE SPAN 2 DECK | 160 | Hr(s) | 160 | Hr(s) | 360 | Hr(s) | 256 | Hr(s) |
| A1840 | SB FABRICATE SPAN 3 T-BEAMS | 160 | Hr(s) | 160 | Hr(s) | 264 | Hr(s) | 160 | Hr(s) |
| A2070 | SB FABRICATE SPAN 3 DECK | 160 | Hr(s) | 160 | Hr(s) | 360 | Hr(s) | 256 | Hr(s) |
| A1260 | SB FABRICATE SPAN 1 EDGE-BEAMS | 160 | Hr(s) | 160 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A1270 | SB FABRICATE SPAN 1 DECK | 160 | Hr(s) | 160 | Hr(s) | 168 | Hr(s) | 80 | Hr(s) |
| A1850 | SB FABRICATE BENT 2 EDGE BEAM | 160 | Hr(s) | 160 | Hr(s) | 360 | Hr(s) | 216 | Hr(s) |
| A2080 | SB FABRICATE BENT 3 EDGE BEAM | 160 | Hr(s) | 160 | Hr(s) | 360 | Hr(s) | 216 | Hr(s) |
| A2380 | SB FABRICATE BENT 4 EDGE BEAM | 160 | Hr(s) | 160 | Hr(s) | 360 | Hr(s) | 216 | Hr(s) |
| A2090 | SB FABRICATE SPAN 4-6 DECK | 160 | Hr(s) | 160 | Hr(s) | 352 | Hr(s) | 248 | Hr(s) |
| A1860 | SB FABRICATE SPAN 7-9 DECK | 160 | Hr(s) | 160 | Hr(s) | 208 | Hr(s) | 144 | Hr(s) |
| A2390 | SB FABRICATE SPAN 1-6 BRIDGE RAIL CURB | 160 | Hr(s) | 160 | Hr(s) | 440 | Hr(s) | 296 | Hr(s) |
| A2550 | SB FABRICATE SPAN 7-9 F-RAIL | 160 | Hr(s) | 160 | Hr(s) | 440 | Hr(s) | 296 | Hr(s) |
| A1870 | SB FABRICATE BENT 1 & 10 END PANELS | 160 | Hr(s) | 160 | Hr(s) | 1096 | Hr(s) | 952 | Hr(s) |
| A3400 | SB STRUCTURE COMPLETE (SB/NB ON) | 0 | Hr(s) | 0 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3130 | NE SOUND WALL - NB - SHOP DRWGS. | 720 | Hr(s) | 720 | Hr(s) | 5784 | Hr(s) | 872 | Hr(s) |
| A1290 | FABRICATE STRIP SEALS - WRB SB | 480 | Hr(s) | 480 | Hr(s) | 1088 | Hr(s) | 944 | Hr(s) |
| A3320 | REMOVE DECOMM DEMO CONTAINMENT | 160 | Hr(s) | 160 | Hr(s) | 984 | Hr(s) | 272 | Hr(s) |
| A3370 | REMOVE WEST WORK BRIDGE | 152 | Hr(s) | 152 | Hr(s) | 984 | Hr(s) | 272 | Hr(s) |
| A3300 | CLASS 1 FINISH 3 TUBE CURB (SPAN 1-6) | 160 | Hr(s) | 160 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3070 | BENT 2 INSTALL EXPANSION JOINTS | 40 | Hr(s) | 40 | Hr(s) | 448 | Hr(s) | 408 | Hr(s) |
| A2230 | BENT 2 EDGE BEAM F/P/S | 80 | Hr(s) | 80 | Hr(s) | 560 | Hr(s) | 432 | Hr(s) |
| A2400 | BENT 3 EDGE BEAM F/P/S | 80 | Hr(s) | 80 | Hr(s) | 480 | Hr(s) | 352 | Hr(s) |
| A2570 | BENT 4 EDGE BEAM F/P/S | 80 | Hr(s) | 80 | Hr(s) | 360 | Hr(s) | 216 | Hr(s) |
| A3350 | SB STRUCTURE COMPLETE (SB ON) | 0 | Hr(s) | 0 | Hr(s) | 152 | Hr(s) | 112 | Hr(s) |
| A3120 | NB REBAR - SHAFTS/FTGS | 480 | Hr(s) | 480 | Hr(s) | 1056 | Hr(s) | 896 | Hr(s) |
| A2160 | BENT 1 BACKFILL | 32 | Hr(s) | 32 | Hr(s) | 1072 | Hr(s) | 928 | Hr(s) |
| A2260 | BENT 1 END PANEL | 64 | Hr(s) | 64 | Hr(s) | 1048 | Hr(s) | 904 | Hr(s) |
| A2970 | BENT 4 CLOSURE POUR COMPLETE | 80 | Hr(s) | 80 | Hr(s) | 472 | Hr(s) | 408 | Hr(s) |
| A3050 | BENT 4 INSTALL EXPANSION JOINT | 40 | Hr(s) | 40 | Hr(s) | 472 | Hr(s) | 408 | Hr(s) |
| A3220 | BENT 7 INSTALL EXPANSION JOINT | 80 | Hr(s) | 80 | Hr(s) | 344 | Hr(s) | 280 | Hr(s) |
| A2660 | BENT 10 F/P/S BACKWALL | 80 | Hr(s) | 80 | Hr(s) | 576 | Hr(s) | 512 | Hr(s) |
| A3010 | BENT 10 JACK END BENT / BEARINGS | 8 | Hr(s) | 8 | Hr(s) | 576 | Hr(s) | 512 | Hr(s) |
| A2730 | BENT 10 BACKFILL | 32 | Hr(s) | 32 | Hr(s) | 576 | Hr(s) | 512 | Hr(s) |
| A2780 | BENT 10 END PANELS | 64 | Hr(s) | 64 | Hr(s) | 576 | Hr(s) | 512 | Hr(s) |
| A1310 | SPAN 1 PRECAST FLOOR BEAMS | 24 | Hr(s) | 24 | Hr(s) | 240 | Hr(s) | 152 | Hr(s) |
| A1730 | SPAN 1 T-BEAMS | 64 | Hr(s) | 64 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A1810 | SPAN 1 DECK | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A2940 | BENT 10 INSTALL EXPANSION JOINT | 40 | Hr(s) | 40 | Hr(s) | 576 | Hr(s) | 512 | Hr(s) |
| A2890 | BENT 10 F/P/S EXPANSION JOINT | 40 | Hr(s) | 40 | Hr(s) | 576 | Hr(s) | 512 | Hr(s) |
| A1910 | SPAN 1 DECK CURE | 112 | Hr(s) | 112 | Hr(s) | 152 | Hr(s) | 32 | Hr(s) |
| A2050 | SPAN 1 POST-TENSIONING & GROUT/BLK OUTS | 56 | Hr(s) | 56 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A2580 | SPAN 1 BRIDGE RAIL CURB | 48 | Hr(s) | 48 | Hr(s) | 720 | Hr(s) | 576 | Hr(s) |
| A2610 | SPAN 1 STRIP FORMWORK | 80 | Hr(s) | 80 | Hr(s) | 2144 | Hr(s) | 1456 | Hr(s) |
| A2710 | SPAN 1 FINISH WORK | 80 | Hr(s) | 80 | Hr(s) | 2144 | Hr(s) | 1456 | Hr(s) |
| A2810 | SPAN 1 REMOVE FALSEWORK | 40 | Hr(s) | 40 | Hr(s) | 3968 | Hr(s) | 1720 | Hr(s) |
| A1130 | SPAN 2 REMOVE ARCH RIB FALSEWORK | 120 | Hr(s) | 120 | Hr(s) | 288 | Hr(s) | 200 | Hr(s) |
| A1320 | SPAN 2 T-BEAM FALSEWORK | 256 | Hr(s) | 256 | Hr(s) | 288 | Hr(s) | 200 | Hr(s) |
| A2170 | SPAN 2 FORM T-BEAMS | 160 | Hr(s) | 160 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A2440 | SPAN 2 REBAR T-BEAMS | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A2450 | SPAN 2 ERECT FLOOR PRECAST BEAMS | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A2490 | SPAN 2 POUR T-BEAMS | 16 | Hr(s) | 16 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A2530 | SPAN 2 DECK FORMING | 240 | Hr(s) | 240 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A2620 | SPAN 2 DECK REBAR | 160 | Hr(s) | 160 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A2820 | SPAN 2 BIDWELL SETUP / DRY RUN | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A2910 | SPAN 2 POUR DECK | 24 | Hr(s) | 24 | Hr(s) | 104 | Hr(s) | 16 | Hr(s) |
| A2960 | SPAN 2 CURE DECK | 80 | Hr(s) | 80 | Hr(s) | 152 | Hr(s) | 16 | Hr(s) |
| A3040 | SPAN 2 STRIP T-BEAMS | 56 | Hr(s) | 56 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3080 | SPAN 2 REMOVE T-BEAM F/W | 160 | Hr(s) | 160 | Hr(s) | 1752 | Hr(s) | 1104 | Hr(s) |
| A3090 | SPAN 2 T/EDGE/DECK CLOSURE POUR - F/P/S | 160 | Hr(s) | 160 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3250 | SPAN 2 BRIDGE RAIL CURB | 64 | Hr(s) | 64 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3260 | SPAN 2 STRIP EDGE-BEAM FALSEWORK | 120 | Hr(s) | 120 | Hr(s) | 1752 | Hr(s) | 1104 | Hr(s) |
| A1470 | SPAN 3 JACKING ARCH | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A1540 | SPAN 3 ARCH RIB CLOSURE | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A1550 | SPAN 3 REMOVE ARCH RIB FALSEWORK | 120 | Hr(s) | 120 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A1610 | SPAN 3 T BEAM FALSEWORK | 256 | Hr(s) | 256 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A2100 | SPAN 3 FORM T-BEAMS | 160 | Hr(s) | 160 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A2410 | SPAN 3 REBAR T-BEAMS | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A2420 | SPAN 3 ERECTFLOOR PRECAST BEAMS | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A2460 | SPAN 3 POUR T-BEAMS | 16 | Hr(s) | 16 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A2470 | SPAN 3 DECK FORMING | 320 | Hr(s) | 320 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A2690 | SPAN 3 DECK REBAR | 160 | Hr(s) | 160 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A2850 | SPAN 3 BIDWELL SETUP / DRY RUN | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A2980 | SPAN 3 POUR DECK | 24 | Hr(s) | 24 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A3020 | SPAN 3 CURE DECK | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A3100 | SPAN 3 STRIP T-BEAMS | 56 | Hr(s) | 56 | Hr(s) | 1976 | Hr(s) | 1232 | Hr(s) |
| A3110 | SPAN 3 T/EDGE/DECK CLOSURE POUR - F/P/S | 160 | Hr(s) | 160 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A3210 | SPAN 3 REMOVE T-BEAM F/W | 160 | Hr(s) | 160 | Hr(s) | 1976 | Hr(s) | 1232 | Hr(s) |
| A3270 | SPAN 3 BRIDGE RAIL CURB | 64 | Hr(s) | 64 | Hr(s) | 104 | Hr(s) | 64 | Hr(s) |
| A3280 | SPAN 3 STRIP EDGE-BEAM FALSEWORK | 120 | Hr(s) | 120 | Hr(s) | 1992 | Hr(s) | 1168 | Hr(s) |
| A1460 | SPAN 4 POUR BOTTOM SLAB 1a | 8 | Hr(s) | 8 | Hr(s) | 584 | Hr(s) | 504 | Hr(s) |
| A1480 | SPAN 4 STRIP BULKHEADS SLAB 1a | 8 | Hr(s) | 8 | Hr(s) | 584 | Hr(s) | 504 | Hr(s) |
| A1580 | SPAN 6 INSTALL REBAR X-BEAM/ STEM | 32 | Hr(s) | 32 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A1620 | SPAN 6 INSTALL PT DUCT & TRUMPETS | 32 | Hr(s) | 32 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A1510 | SPAN 6 REBAR BOTTOM SLAB | 32 | Hr(s) | 32 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2130 | SPAN 4 FORM STEM WALLS 2a | 64 | Hr(s) | 64 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2240 | SPAN 4 FORM DIAHPHRAGMS 2a | 24 | Hr(s) | 24 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2270 | SPAN 4 POUR STEMS/ DIAPHRAGMS 2a | 8 | Hr(s) | 8 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2300 | SPAN 4 STRIP STEMS / DIAHPHRAGMS 2a | 16 | Hr(s) | 16 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2350 | SPAN 4 F/R STEM WALLS /X-BEAM 2b | 16 | Hr(s) | 16 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2360 | SPAN 4 POUR STEM WALLS/X-BEAM 2b | 8 | Hr(s) | 8 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2540 | SPAN 4-6 DECK REBAR | 120 | Hr(s) | 120 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2630 | SPAN 4-6 SETUP BIDWELL / DRY RUN (4-6) | 24 | Hr(s) | 24 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2740 | SPAN 4-6 POUR DECK | 8 | Hr(s) | 8 | Hr(s) | 208 | Hr(s) | 144 | Hr(s) |
| A2770 | SPAN 4-6 CURE DECK | 80 | Hr(s) | 80 | Hr(s) | 208 | Hr(s) | 144 | Hr(s) |
| A2860 | SPAN 4-6 POST TENSIONING & BLOCKOUTS | 80 | Hr(s) | 80 | Hr(s) | 208 | Hr(s) | 144 | Hr(s) |
| A2990 | SPAN 4-6 STRIP DECK | 80 | Hr(s) | 80 | Hr(s) | 392 | Hr(s) | 328 | Hr(s) |
| A3240 | SPAN 4-6 FINISH WORK | 480 | Hr(s) | 480 | Hr(s) | 4040 | Hr(s) | 1336 | Hr(s) |
| A2370 | SPAN 4 STRIP STEM WALLS / X-BEAM 2b | 40 | Hr(s) | 40 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2430 | SPAN 4 FORM DECK/ OVERHANG/EOD | 80 | Hr(s) | 80 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2870 | SPAN 4-6 BRIDGE RAIL CURB | 160 | Hr(s) | 160 | Hr(s) | 352 | Hr(s) | 288 | Hr(s) |
| A3060 | SPAN 4-6 FALSEWORK REMOVAL | 120 | Hr(s) | 120 | Hr(s) | 392 | Hr(s) | 328 | Hr(s) |
| A1390 | SPAN 9 POUR STEM WALLS/X-BEAM 2b | 8 | Hr(s) | 8 | Hr(s) | 328 | Hr(s) | 0 | Hr(s) |
| A1400 | SPAN 9 STRIP STEM WALLS / X-BEAM 2b | 16 | Hr(s) | 16 | Hr(s) | 328 | Hr(s) | 0 | Hr(s) |
| A1420 | SPAN 9 FORM DECK/ OVERHANG/EOD | 80 | Hr(s) | 80 | Hr(s) | 328 | Hr(s) | 0 | Hr(s) |
| A2110 | SPAN 7-9 DECK REBAR | 120 | Hr(s) | 120 | Hr(s) | 208 | Hr(s) | 144 | Hr(s) |
| A2340 | SPAN 7-9 SETUP BIDWELL / DRY RUN (4-6) | 24 | Hr(s) | 24 | Hr(s) | 208 | Hr(s) | 144 | Hr(s) |
| A2480 | SPAN 7-9 POUR DECK | 24 | Hr(s) | 24 | Hr(s) | 208 | Hr(s) | 144 | Hr(s) |
| A2520 | SPAN 7-9 CURE DECK | 80 | Hr(s) | 80 | Hr(s) | 208 | Hr(s) | 144 | Hr(s) |
| A2590 | SPAN 7-9 POST TENSIONING & BLOCKOUTS | 80 | Hr(s) | 80 | Hr(s) | 208 | Hr(s) | 144 | Hr(s) |
| A2670 | SPAN 7-9 STRIP DECK | 80 | Hr(s) | 80 | Hr(s) | 640 | Hr(s) | 576 | Hr(s) |
| A2680 | SPAN 7-9 PT CLOSURE (POUR WITH SPAN 4-6) | 80 | Hr(s) | 80 | Hr(s) | 208 | Hr(s) | 144 | Hr(s) |
| A2900 | SPAN 7-9 FINISH WORK | 480 | Hr(s) | 480 | Hr(s) | 4288 | Hr(s) | 1584 | Hr(s) |
| A2750 | SPAN 7-9 FALSEWORK REMOVAL | 120 | Hr(s) | 120 | Hr(s) | 640 | Hr(s) | 576 | Hr(s) |
| A2760 | SPAN 7-9 CLOSURE POUR CURE | 80 | Hr(s) | 80 | Hr(s) | 520 | Hr(s) | 456 | Hr(s) |
| A2720 | FORM/STRIP F-RAIL (SPAN 7-9) | 152 | Hr(s) | 152 | Hr(s) | 440 | Hr(s) | 296 | Hr(s) |
| A3030 | F-RAIL CLASS 1 FINISH (SPAN 7-9) | 120 | Hr(s) | 120 | Hr(s) | 440 | Hr(s) | 296 | Hr(s) |
| A3310 | INSTALL 3 TUBE RAILING (SPAN 1-6) | 160 | Hr(s) | 160 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A2310 | REMOVE WORK BRIDGE/CONTAINMENT | 40 | Hr(s) | 40 | Hr(s) | 1096 | Hr(s) | 1032 | Hr(s) |
| A3230 | CONCRETE SLOPE PAVING | 48 | Hr(s) | 48 | Hr(s) | 6616 | Hr(s) | 1704 | Hr(s) |
| A2790 | AC SHOULDERS | 0 | Hr(s) | 0 | Hr(s) | 544 | Hr(s) | 880 | Hr(s) |
| A3340 | SWITCH SB TRAFFIC ONTO NEW SB BRIDGE | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A2500 | INSTALL CRCP PAVEMENT | 160 | Hr(s) | 160 | Hr(s) | 544 | Hr(s) | 880 | Hr(s) |
| A3330 | SB BRIDGE READY FOR SB TRAFFIC | 0 | Hr(s) | 0 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A2800 | INSTALL CONC. SHLDR. BARRIER | 24 | Hr(s) | 24 | Hr(s) | 544 | Hr(s) | 880 | Hr(s) |
| A3410 | NB DEMO DETOUR SPAN 1 | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3430 | NB DEMO DETOUR SPAN 2 (New Bnt. 2) | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A2950 | PLACE/CURE 42 F-RAIL (SPAN 7-9) | 56 | Hr(s) | 56 | Hr(s) | 440 | Hr(s) | 296 | Hr(s) |
| A2880 | INSTALL TEMP. BRIDGE DRAINAGE SYSTEM | 160 | Hr(s) | 160 | Hr(s) | 512 | Hr(s) | 448 | Hr(s) |
| A3190 | SLOPE PAVING CURBS | 40 | Hr(s) | 40 | Hr(s) | 6616 | Hr(s) | 1704 | Hr(s) |
| A1340 | FINISH WORK | 80 | Hr(s) | 80 | Hr(s) | 1528 | Hr(s) | 1384 | Hr(s) |
| A3440 | NB DEMO DETOUR SPAN 3 (River) | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3530 | NB DEMO DETOUR SPAN 4 (River) | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3630 | NB DEMO DETOUR SPAN 7 (River) | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3680 | NB DEMO DETOUR SPAN 8 (River) | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3720 | NB DEMO DETOUR SPAN 9 (New Bnt. 4) | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A4220 | NB DEMO DETOUR SPAN 11 | 40 | Hr(s) | 40 | Hr(s) | 864 | Hr(s) | 120 | Hr(s) |
| A3760 | NB DEMO DETOUR SPAN 10 | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A2830 | INSTALL GUARDRAIL | 16 | Hr(s) | 16 | Hr(s) | 688 | Hr(s) | 1024 | Hr(s) |
| A4160 | NB DEMO DETOUR SPAN 12 | 40 | Hr(s) | 40 | Hr(s) | 864 | Hr(s) | 120 | Hr(s) |
| A4080 | NB DEMO DETOUR SPAN 13 | 40 | Hr(s) | 40 | Hr(s) | 864 | Hr(s) | 120 | Hr(s) |
| A3880 | NB DEMO DETOUR SPAN 16 (Pre-cast) | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3840 | NB DEMO DEOTUR SPAN 17 | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3550 | NB DEMO DETOUR SPAN 5 (River) (New Bnt. 3) | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3600 | NB DEMO DETOUR SPAN 6 (River) | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A3990 | NB DEMO DETOUR SPAN 14 | 40 | Hr(s) | 40 | Hr(s) | 864 | Hr(s) | 120 | Hr(s) |
| A3930 | NB DEMO DETOUR SPAN 15 (RR Pre-cast) | 40 | Hr(s) | 40 | Hr(s) | 152 | Hr(s) | 0 | Hr(s) |
| A2840 | INSTALL PERM. SIGNING | 160 | Hr(s) | 160 | Hr(s) | 544 | Hr(s) | 880 | Hr(s) |
| A4060 | NBBB BENT 1 STRUCTURE EXCAVATION | 16 | Hr(s) | 16 | Hr(s) | 2264 | Hr(s) | 56 | Hr(s) |
| A4090 | NBBB BENT 1 DRIVEN PILE | 40 | Hr(s) | 40 | Hr(s) | 2264 | Hr(s) | 56 | Hr(s) |
| A1350 | INSTALL CONCR. SHLDR. BARRIER | 8 | Hr(s) | 8 | Hr(s) | 1640 | Hr(s) | 0 | Hr(s) |
| A4170 | NBBB BENT 1 CAP | 80 | Hr(s) | 80 | Hr(s) | 2264 | Hr(s) | 56 | Hr(s) |
| A4280 | NBBB BENT 1 BACK WALL - F/P/S | 80 | Hr(s) | 80 | Hr(s) | 3008 | Hr(s) | 200 | Hr(s) |
| A2250 | INSTALL CRCP PAVEMENT | 160 | Hr(s) | 160 | Hr(s) | 544 | Hr(s) | 880 | Hr(s) |
| A4480 | NBBB BENT 1 WINGWALLS | 80 | Hr(s) | 80 | Hr(s) | 3008 | Hr(s) | 200 | Hr(s) |
| A2640 | INSTALL CONC. SHLDR. BARRIER | 16 | Hr(s) | 16 | Hr(s) | 832 | Hr(s) | 1168 | Hr(s) |
| A3770 | NBBB BENT 2 STRUCTURE EXC | 24 | Hr(s) | 24 | Hr(s) | 200 | Hr(s) | 56 | Hr(s) |
| A2510 | INSTALL TERM. EXP. JOINT | 120 | Hr(s) | 120 | Hr(s) | 832 | Hr(s) | 1168 | Hr(s) |
| A3830 | NBBB BENT 2 COFFERDAM & DRILLER ACCESS | 160 | Hr(s) | 160 | Hr(s) | 200 | Hr(s) | 56 | Hr(s) |
| A2600 | PAVE AC SHOULDERS | 40 | Hr(s) | 40 | Hr(s) | 832 | Hr(s) | 1168 | Hr(s) |
| A3360 | TEMP. PAVING / DRAINAGE - SOUTH END | 120 | Hr(s) | 120 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A4070 | NBBB BENT 2 DRILLED SHAFTS #1 | 112 | Hr(s) | 112 | Hr(s) | 200 | Hr(s) | 80 | Hr(s) |
| A4250 | NBBB BENT 2 CSL TESTING | 24 | Hr(s) | 24 | Hr(s) | 200 | Hr(s) | 80 | Hr(s) |
| A4290 | NBBB BENT 2 ARCH SEATS | 120 | Hr(s) | 120 | Hr(s) | 200 | Hr(s) | 80 | Hr(s) |
| A4550 | NBBB BENT 2 COLUMNS | 120 | Hr(s) | 120 | Hr(s) | 200 | Hr(s) | 120 | Hr(s) |
| A3380 | ESTABLISH TRAFFIC CONTROL MEASURES | 40 | Hr(s) | 40 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A4260 | NBBB BENT 3 DRILLED SHAFTS #1 | 56 | Hr(s) | 56 | Hr(s) | 784 | Hr(s) | 144 | Hr(s) |
| A4370 | NBBB BENT 3 CSL TESTING | 24 | Hr(s) | 24 | Hr(s) | 784 | Hr(s) | 144 | Hr(s) |
| A4560 | NBBB BENT 3 ARCH SEATS | 160 | Hr(s) | 160 | Hr(s) | 720 | Hr(s) | 80 | Hr(s) |
| A3790 | NBBB BENT 5 INSTALL SHORING | 40 | Hr(s) | 40 | Hr(s) | 1064 | Hr(s) | 320 | Hr(s) |
| A3850 | NBBB BENT 5 STRUCTURE EXCAVATION | 40 | Hr(s) | 40 | Hr(s) | 1312 | Hr(s) | 440 | Hr(s) |
| A4380 | NBBB BENT 5 DRILLED SHAFTS#1 | 56 | Hr(s) | 56 | Hr(s) | 1040 | Hr(s) | 168 | Hr(s) |
| A4500 | NBBB BENT 5 CSL TESTING | 24 | Hr(s) | 24 | Hr(s) | 1040 | Hr(s) | 168 | Hr(s) |
| A4490 | NBBB BENT 6 CSL TESTING | 24 | Hr(s) | 24 | Hr(s) | 840 | Hr(s) | 96 | Hr(s) |
| A4520 | NBBB BENT 6 COLUMNS | 80 | Hr(s) | 80 | Hr(s) | 840 | Hr(s) | 96 | Hr(s) |
| A3780 | NBBB BENT 4 DRILLED SHAFTS #2 | 112 | Hr(s) | 112 | Hr(s) | 112 | Hr(s) | 104 | Hr(s) |
| A3920 | NBBB BENT 4 CSL TESTING | 24 | Hr(s) | 24 | Hr(s) | 1184 | Hr(s) | 544 | Hr(s) |
| A4680 | NBBB BENT 5 COLUMNS | 80 | Hr(s) | 80 | Hr(s) | 968 | Hr(s) | 96 | Hr(s) |
| A4330 | NBBB BENT 6 DRILLED SHAFTS #1 | 56 | Hr(s) | 56 | Hr(s) | 840 | Hr(s) | 96 | Hr(s) |
| A4130 | NBBB BENT 7 INSTALL SHORING | 40 | Hr(s) | 40 | Hr(s) | 176 | Hr(s) | 96 | Hr(s) |
| A4210 | NBBB BENT 7 STRUCUTRE EXCAVATION | 16 | Hr(s) | 16 | Hr(s) | 176 | Hr(s) | 96 | Hr(s) |
| A4230 | NBBB BENT 7 DRILLED SHAFTS #1 | 56 | Hr(s) | 56 | Hr(s) | 176 | Hr(s) | 96 | Hr(s) |
| A4340 | NBBB BENT 7 CSL TESTING | 24 | Hr(s) | 24 | Hr(s) | 176 | Hr(s) | 168 | Hr(s) |
| A4030 | NBBB BENT 8 INSTALL SHORING | 40 | Hr(s) | 40 | Hr(s) | 152 | Hr(s) | 96 | Hr(s) |
| A4120 | NBBB BENT 8 STRUCTRE EXCAVATION | 16 | Hr(s) | 16 | Hr(s) | 152 | Hr(s) | 96 | Hr(s) |
| A4140 | NBBB BENT 8 DRILLED SHAFTS #2 | 56 | Hr(s) | 56 | Hr(s) | 152 | Hr(s) | 144 | Hr(s) |
| A4240 | NBBB BENT 8 CSL TESTING | 24 | Hr(s) | 24 | Hr(s) | 152 | Hr(s) | 144 | Hr(s) |
| A4270 | NBBB BENT 8 F/P/S FOOTING | 64 | Hr(s) | 64 | Hr(s) | 152 | Hr(s) | 144 | Hr(s) |
| A4530 | NBBB BENT 8 COLUMNS | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 96 | Hr(s) |
| A4000 | NBBB BENT 9 DRILLER ACCESS | 16 | Hr(s) | 16 | Hr(s) | 152 | Hr(s) | 96 | Hr(s) |
| A4040 | NBBB BENT 9 DRILLED SHAFTS #2 | 56 | Hr(s) | 56 | Hr(s) | 152 | Hr(s) | 144 | Hr(s) |
| A4420 | NBBB BENT 7 F/P/S FOOTING | 64 | Hr(s) | 64 | Hr(s) | 168 | Hr(s) | 160 | Hr(s) |
| A4690 | NBBB BENT 7 COLUMNS | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 96 | Hr(s) |
| A4150 | NBBB BENT 9 CSL TESTING | 24 | Hr(s) | 24 | Hr(s) | 192 | Hr(s) | 184 | Hr(s) |
| A4350 | NBBB BENT 9 COLUMN | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 96 | Hr(s) |
| A3940 | NBBB BENT 10 DRILLED SHAFTS #2 | 56 | Hr(s) | 56 | Hr(s) | 104 | Hr(s) | 96 | Hr(s) |
| A4050 | NBBB BENT 10 CSL TESTING | 24 | Hr(s) | 24 | Hr(s) | 104 | Hr(s) | 96 | Hr(s) |
| A4100 | NBBB BENT 10 F/P/S FOOTINGS | 64 | Hr(s) | 64 | Hr(s) | 104 | Hr(s) | 96 | Hr(s) |
| A4200 | NBBB BENT 10 COLUMN | 80 | Hr(s) | 80 | Hr(s) | 104 | Hr(s) | 96 | Hr(s) |
| A3890 | NBBB BENT 11 STRUCTURE EXC | 40 | Hr(s) | 40 | Hr(s) | 192 | Hr(s) | 136 | Hr(s) |
| A4620 | NBBB BENT 11 DRIVE PILE | 40 | Hr(s) | 40 | Hr(s) | 2728 | Hr(s) | 80 | Hr(s) |
| A4300 | SPAN 1 FALSEWORK | 160 | Hr(s) | 160 | Hr(s) | 2264 | Hr(s) | 56 | Hr(s) |
| A4630 | SPAN 1 PRECAST TRANS BEAMS | 24 | Hr(s) | 24 | Hr(s) | 2264 | Hr(s) | 56 | Hr(s) |
| A4700 | SPAN 1 T-BEAMS | 120 | Hr(s) | 120 | Hr(s) | 2264 | Hr(s) | 56 | Hr(s) |
| A3570 | NBAA BENT 1 STRUCTURE EXCAVATION | 16 | Hr(s) | 16 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A3580 | NBAA BENT 1 PILE | 40 | Hr(s) | 40 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A2650 | INSTALL CRCP TERM. EXP. JOINT | 120 | Hr(s) | 120 | Hr(s) | 544 | Hr(s) | 880 | Hr(s) |
| A3620 | NBAA BENT 1 CAP | 80 | Hr(s) | 80 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A3640 | NBAA BENT 1 CURE CAP | 80 | Hr(s) | 80 | Hr(s) | 704 | Hr(s) | 104 | Hr(s) |
| A3650 | NBAA MSE WALL #21315 | 80 | Hr(s) | 80 | Hr(s) | 1000 | Hr(s) | 400 | Hr(s) |
| A3690 | NBAA BENT 1 BACKFILL | 32 | Hr(s) | 32 | Hr(s) | 1016 | Hr(s) | 416 | Hr(s) |
| A3590 | NBAA BENT 2 STRUCTURE EXCAVATION | 16 | Hr(s) | 16 | Hr(s) | 688 | Hr(s) | 88 | Hr(s) |
| A3610 | NBAA BENT 2 PILE | 40 | Hr(s) | 40 | Hr(s) | 688 | Hr(s) | 88 | Hr(s) |
| A3660 | NBAA BENT 2 CAP | 80 | Hr(s) | 80 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A3700 | NBAA BENT 2 CURE CAP | 80 | Hr(s) | 80 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A3710 | NBAA MSE WALL #21316 | 80 | Hr(s) | 80 | Hr(s) | 1000 | Hr(s) | 400 | Hr(s) |
| A3740 | NBAA BENT 2 BACKFILL | 32 | Hr(s) | 32 | Hr(s) | 1000 | Hr(s) | 400 | Hr(s) |
| A3750 | NBAA SPAN 1 ERECT BEAMS | 16 | Hr(s) | 16 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A3800 | NBAA SPAN 1 DIAPHRAGMS & END WALLS | 120 | Hr(s) | 120 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A3950 | NBAA SPAN 1 FORM DECK | 120 | Hr(s) | 120 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A4180 | NBAA SPAN 1 POUR DECK | 8 | Hr(s) | 8 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A4190 | NBAA SPAN 1 DECK CURE | 112 | Hr(s) | 112 | Hr(s) | 896 | Hr(s) | 40 | Hr(s) |
| A4320 | NBAA BENT 1 END PANEL | 64 | Hr(s) | 64 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A4450 | NBAA BENT 2 END PANEL | 64 | Hr(s) | 64 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A4580 | NBAA SPAN 1 BRIDGE RAIL | 80 | Hr(s) | 80 | Hr(s) | 624 | Hr(s) | 144 | Hr(s) |
| A3810 | CLOSE FN1 OFFRAMP | 0 | Hr(s) | 0 | Hr(s) | 4104 | Hr(s) | 160 | Hr(s) |
| A3820 | OBLITERATE ROADWAY | 32 | Hr(s) | 32 | Hr(s) | 4360 | Hr(s) | 384 | Hr(s) |
| A3960 | EXCAVATION/EMBANKMENT | 160 | Hr(s) | 160 | Hr(s) | 4272 | Hr(s) | 296 | Hr(s) |
| A3970 | CONSTRUCT DT6 DITCH | 40 | Hr(s) | 40 | Hr(s) | 4312 | Hr(s) | 336 | Hr(s) |
| A4010 | CONSTRUCT SW5 SWALE | 80 | Hr(s) | 80 | Hr(s) | 4312 | Hr(s) | 336 | Hr(s) |
| A4110 | INSTALL DRAINAGE | 120 | Hr(s) | 120 | Hr(s) | 4232 | Hr(s) | 336 | Hr(s) |
| A4310 | AGGREGATE BASE | 32 | Hr(s) | 32 | Hr(s) | 4232 | Hr(s) | 296 | Hr(s) |
| A4460 | PERMANENT SHOULDER BARRIER | 24 | Hr(s) | 24 | Hr(s) | 5128 | Hr(s) | 296 | Hr(s) |
| A4390 | AC BASE PAVING | 16 | Hr(s) | 16 | Hr(s) | 4232 | Hr(s) | 296 | Hr(s) |
| A4400 | INSTALL TEMPORARY BARRIER | 16 | Hr(s) | 16 | Hr(s) | 4232 | Hr(s) | 328 | Hr(s) |
| A4410 | TEMPORARY STRIPING | 8 | Hr(s) | 8 | Hr(s) | 4248 | Hr(s) | 296 | Hr(s) |
| A4430 | AC TOP LIFT PAVING - RAMP | 16 | Hr(s) | 16 | Hr(s) | 3072 | Hr(s) | 296 | Hr(s) |
| A3420 | WORK BRIDGE | 160 | Hr(s) | 160 | Hr(s) | 728 | Hr(s) | 24 | Hr(s) |
| A3520 | NBAA DETOUR BRIDGE REMOVAL | 160 | Hr(s) | 160 | Hr(s) | 624 | Hr(s) | 24 | Hr(s) |
| A4440 | INSTALL PERM. SIGNING | 8 | Hr(s) | 8 | Hr(s) | 4232 | Hr(s) | 328 | Hr(s) |
| A4510 | PERMANENT STRIPING | 8 | Hr(s) | 8 | Hr(s) | 5128 | Hr(s) | 296 | Hr(s) |
| A3560 | INSTALL PERMANENT DRAINAGE | 120 | Hr(s) | 120 | Hr(s) | 3968 | Hr(s) | 880 | Hr(s) |
| A3490 | GENERAL EXCAVATION | 120 | Hr(s) | 120 | Hr(s) | 3968 | Hr(s) | 880 | Hr(s) |
| A4470 | AGGREGATE BASE | 120 | Hr(s) | 120 | Hr(s) | 3336 | Hr(s) | 128 | Hr(s) |
| A3510 | EMBANKMENT | 80 | Hr(s) | 80 | Hr(s) | 4008 | Hr(s) | 920 | Hr(s) |
| A4590 | OBLITERATE ROADWAY | 40 | Hr(s) | 40 | Hr(s) | 3192 | Hr(s) | 24 | Hr(s) |
| A4660 | GENERAL EXCAVATION | 160 | Hr(s) | 160 | Hr(s) | 3192 | Hr(s) | 24 | Hr(s) |
| A3290 | PROJECT LANDSCAPING - SB | 480 | Hr(s) | 480 | Hr(s) | 3744 | Hr(s) | 928 | Hr(s) |
| A4670 | EMBANKMENT | 40 | Hr(s) | 40 | Hr(s) | 3312 | Hr(s) | 144 | Hr(s) |
| A3670 | AGGREGATE BASE | 120 | Hr(s) | 120 | Hr(s) | 4328 | Hr(s) | 600 | Hr(s) |
| A3470 | EMBANKMENT | 120 | Hr(s) | 120 | Hr(s) | 4328 | Hr(s) | 600 | Hr(s) |
| A3730 | AC BASE PAVING | 80 | Hr(s) | 80 | Hr(s) | 4328 | Hr(s) | 600 | Hr(s) |
| A3860 | PERM CONCRETE SHOULDER BARRIER | 40 | Hr(s) | 40 | Hr(s) | 4328 | Hr(s) | 600 | Hr(s) |
| A4640 | NE SOUNDWALL LN1 655+00 | 200 | Hr(s) | 200 | Hr(s) | 4872 | Hr(s) | 0 | Hr(s) |
| A3540 | INSTALL PERMANENT DRAINAGE | 240 | Hr(s) | 240 | Hr(s) | 4328 | Hr(s) | 600 | Hr(s) |
| A3450 | GENERAL EXCAVATION | 40 | Hr(s) | 40 | Hr(s) | 4328 | Hr(s) | 600 | Hr(s) |
| A3900 | INSTALL PERMENANT FENCING | 80 | Hr(s) | 80 | Hr(s) | 4328 | Hr(s) | 600 | Hr(s) |
| A3390 | SWITCH NB TRAFFIC TO SB BRIDGE | 8 | Hr(s) | 8 | Hr(s) | 104 | Hr(s) | 0 | Hr(s) |
| A4710 | NBBB BENT 6 STRUCTURE BACKFILL | 56 | Hr(s) | 56 | Hr(s) | 840 | Hr(s) | 120 | Hr(s) |
| A3870 | NBBB BENT 6 INSTALL SHORING | 40 | Hr(s) | 40 | Hr(s) | 1064 | Hr(s) | 320 | Hr(s) |
| A3910 | NBBB BENT 6 STRUCTURE EXCAVATION | 40 | Hr(s) | 40 | Hr(s) | 1064 | Hr(s) | 320 | Hr(s) |
| A1160 | SPAN 4 REBAR BOTTOM SLAB | 32 | Hr(s) | 32 | Hr(s) | 296 | Hr(s) | 192 | Hr(s) |
| A1410 | SPAN 4 INSTALL PT DUCT | 24 | Hr(s) | 24 | Hr(s) | 336 | Hr(s) | 0 | Hr(s) |
| A1360 | SPAN 8 FORM STEM WALLS 2a | 64 | Hr(s) | 64 | Hr(s) | 296 | Hr(s) | 0 | Hr(s) |
| A1090 | SPAN 7 FORM STEM WALLS 2a | 64 | Hr(s) | 64 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A3000 | 60 DAY CURE FOR PERM. EXPANSION JOINT | 240 | Hr(s) | 240 | Hr(s) | 488 | Hr(s) | 408 | Hr(s) |
| A1170 | SPAN 4 REBAR STEMS/X-BEAM | 32 | Hr(s) | 32 | Hr(s) | 336 | Hr(s) | 256 | Hr(s) |
| A1430 | SPAN 7 POUR STEM WALLS 2a | 8 | Hr(s) | 8 | Hr(s) | 240 | Hr(s) | 0 | Hr(s) |
| A1440 | SPAN 7 STRIP STEMS/DIAPHRAGMS 2a | 16 | Hr(s) | 16 | Hr(s) | 368 | Hr(s) | 272 | Hr(s) |
| A1140 | SPAN 7 FORM DIAPHRAGMS | 24 | Hr(s) | 24 | Hr(s) | 280 | Hr(s) | 184 | Hr(s) |
| A1370 | SPAN 5 POUR BOTTOM SLAB 1a | 8 | Hr(s) | 8 | Hr(s) | 536 | Hr(s) | 0 | Hr(s) |
| A1770 | SPAN 6 POUR BOTTOM SLAB 1a | 8 | Hr(s) | 8 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A1380 | SPAN 5 STRIP BULKHEADS 1a | 8 | Hr(s) | 8 | Hr(s) | 768 | Hr(s) | 0 | Hr(s) |
| A1780 | SPAN 6 STRIP BULKHEADS 1a | 8 | Hr(s) | 8 | Hr(s) | 584 | Hr(s) | 488 | Hr(s) |
| A1920 | SPAN 5 FORM STEMS 2a | 64 | Hr(s) | 64 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A1790 | SPAN 6 FORM STEMS 2a | 64 | Hr(s) | 64 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2040 | SPAN 5 FORM DIAPHRAGMS | 24 | Hr(s) | 24 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A1880 | SPAN 6 FORM DIAPHRAGMS | 24 | Hr(s) | 24 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2060 | SPAN 5 POUR STEMS/DIAPHRAGMS 2a | 8 | Hr(s) | 8 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A1890 | SPAN 6 POUR STEMS/DIAPHRAGMS 2a | 8 | Hr(s) | 8 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2120 | SPAN 5 STRIP STEMS/DIAPHRAGMS 2a | 16 | Hr(s) | 16 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A1900 | SPAN 6 STRIP STEMS/DIAHPRAGMS 2a | 16 | Hr(s) | 16 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |
| A2140 | SPAN 5 FORM STEMS/X-BEAM 2b | 16 | Hr(s) | 16 | Hr(s) | 376 | Hr(s) | 280 | Hr(s) |
| A1930 | SPAN 6 FORM STEMS/X-BEAM 2b | 16 | Hr(s) | 16 | Hr(s) | 488 | Hr(s) | 392 | Hr(s) |
| A1560 | SPAN 5 POUR BOTTOM SLAB 1b | 8 | Hr(s) | 8 | Hr(s) | 680 | Hr(s) | 600 | Hr(s) |
| A1800 | SPAN 6 POUR BOTTOM SLAB 1b | 8 | Hr(s) | 8 | Hr(s) | 584 | Hr(s) | 488 | Hr(s) |
| A2150 | SPAN 5 POUR STEMS/X-BEAM 2b | 8 | Hr(s) | 8 | Hr(s) | 376 | Hr(s) | 280 | Hr(s) |
| A2000 | SPAN 6 POUR STEMS/X-BEAM 2b | 8 | Hr(s) | 8 | Hr(s) | 488 | Hr(s) | 392 | Hr(s) |
| A2190 | SPAN 5 FORM DECK/OVERHANG | 80 | Hr(s) | 80 | Hr(s) | 376 | Hr(s) | 280 | Hr(s) |
| A2030 | SPAN 6 FORM DECK/OVERHANG | 80 | Hr(s) | 80 | Hr(s) | 488 | Hr(s) | 392 | Hr(s) |
| A2180 | SPAN 5 STRIP STEMS/X-BEAM 2b | 16 | Hr(s) | 16 | Hr(s) | 376 | Hr(s) | 280 | Hr(s) |
| A2010 | SPAN 6 STRIP STEMS/X-BEAM 2b | 16 | Hr(s) | 16 | Hr(s) | 488 | Hr(s) | 392 | Hr(s) |
| A1450 | BENT 7 PT STRIP BLOCKOUTS | 40 | Hr(s) | 40 | Hr(s) | 240 | Hr(s) | 144 | Hr(s) |