If you missed Part 1 of Schedule % Complete in Oracle Primavera, go back now and have a read through. Then come back here. The Proper Setup : Baselined and Cost-loaded Now let’s see how Schedule % Complete works in action on a sample Primavera P6 plan. Since Schedule % Complete is based on both Project Baseline fields and Earned Value Cost fields, to calculate it properly, your schedule
Primavera P6 and Earned Value : Tutorials and Articles
Primavera P6 has powerful Earned Value tracking features. Browse our tutorials and articles on using Earned Value in Primavera P6.
Schedule % Complete in Oracle Primavera – The Missing Guide (Part 1)
71 CommentsSchedule % Complete is one of the many percent completes you have in Primavera P6 and we’re going to have a complete look at what it is and how it is calculated. Two important products of maintaining schedules are planned progress and actual progress of a given time; you want to know how much you’ve done so far and compare it with how much you were supposed to do so far, in order to reach project