Physical Percent Complete in Primavera P6 – the Missing Guide
|

Physical Percent Complete in Primavera P6 – the Missing Guide

There are three different methods of calculating the actual progress of activities: Duration Percent Complete, Units Percent Complete, and Physical Percent Complete. The first two are explained in the previous articles and this article will cover the last one, Physical % Complete. We will also discuss the ways of choosing the appropriate percent complete field…

Units Percent Complete in Primavera P6 – the Missing Guide
|

Units Percent Complete in Primavera P6 – the Missing Guide

This article belongs to a series of articles about units percent complete fields of Primavera P6. As explained in the previous article on the Duration % Complete, there are three percent complete fields for each activity: Duration % Complete Units % Complete Physical % Complete. We’ve already covered Duration % Complete and Schedule % Complete….

Duration Percent Complete in Primavera P6 – the Missing Guide
|

Duration Percent Complete in Primavera P6 – the Missing Guide

There are many different methods for calculation of actual progress in Primavera P6.  These methods involve using many fields and settings, including: Duration % Complete Units % Complete Physical % Complete Activity % Complete Performance % Complete Percent Complete Type Earned Value settings of the WBS Elements I will explain Duration % Complete in this…

Schedule % Complete in Oracle Primavera – The Missing Guide (Part 2)
| |

Schedule % Complete in Oracle Primavera – The Missing Guide (Part 2)

If you missed Part 1 of Schedule % Complete in Oracle Primavera, go back now and have a read through.  Then come back here. The Proper Setup : Baselined and Cost-loaded Now let’s see how Schedule % Complete works in action on a sample Primavera P6 plan. Since Schedule % Complete is based on both…

Schedule % Complete in Oracle Primavera – The Missing Guide (Part 1)
|

Schedule % Complete in Oracle Primavera – The Missing Guide (Part 1)

Schedule % Complete is one of the many percent completes you have in Primavera P6 and we’re going to have a complete look at what it is and how it is calculated.  Two important products of maintaining schedules are planned progress and actual progress of a given time; you want to know how much you’ve…